Notice of Placement in Public Repositories
Utility Trench Excavation Release Abatement Measure (RAM) Plan/Asbestos

The information below was received by US mail on the Haley & Aldrich letterhead.

The letter also included depository locations and contact information for W. R. Grace and for Haley & Aldrich.


UNDERGROUND
ENGINEERING &
ENVIRONMENTAL
SOLUTIONS

Haley & Aldrich, Inc.
465 Medford Street
Suite 2200
Boston, MA 02129-1400
Tel: 617.886.7400
Fax: 617.886.7600
www.HaleyAldrich.com

11 November 2002
File No. 10063-078

Department of Environmental Protection
Northeast Regional Office
205A Lowell Street
Wilmington, Massachusetts 01887

Commissioner of Health and Hospitals
Cambridge Public Health Department
119 Windsor Street
Cambridge, Massachusetts 02139 3606

Subject: Notice of Placement in Public Repositories
Utility Trench Excavation Release Abatement Measure (RAM) Plan/Asbestos
Soil Management Plan (ASMP)
W.R. Grace & Co. Conn.
Cambridge, Massachusetts

To Whom it May Concern:

This letter is to inform you of the placement of the above referenced report, dated 11 November 2002, in five public repositories in accordance with the Public Involvement Plan (PIP) prepared for this site (RTN 3 0277) and in accordance with the City of Cambridge Asbestos Protection
Ordinance (APO).

This RAM Plan/ASMP was prepared in accordance with 3 10 CMR 40.0444 and in accordance with the Cambridge APO. This notice is intended to satisfy the public notification requirements of both the PIP and the Cambridge APO.

In accordance with the PIP prepared for this site comments were accepted on the Public Comment Draft and APO Review Draft RAM Plan/ASMP for 20 days, starting 21 October 2002 and ending at the end of day on 9 November 2002. In accordance with the PIP for this site, the public comment period is now closed. Comments were verbally provided by the City and the DEP. Comments by other parties were not provided.

This letter is also to inform you of the placement of the Commissioner's Final Decision on the Utility Trench Excavation ASMP, dated 11 November 2002, in five public repositories in accordance with the PIP prepared for this site and in accordance with the Cambridge Asbestos APO. In accordance with the APO, please send any comments on the Final Decision to the attention of the following:

Mr. Sam Lipson
Director of Environmental Health
Cambridge Public Health Department
119 Windsor Street
Cambridge, Massachusetts 02139

With the issuance of the Commissioner's Final Decision, this letter is also to inform you of W.R. Grace's intention to begin RAM activities associated with the excavation of this utility trench at the W.R. Grace site. At this time, soil disturbing activities are scheduled to begin on or after 14 November 2002. Activities will be conducted in accordance with the Commissioner's Final Decision and the Utility Trench Excavation Release Abatement Measure (RAM) Plan/Asbestos Soil Management Plan (11 November 2002).

A copy of this letter has been placed in each of the five repositories.

Sincerely yours, HALEY & ALDRICH, INC.


Melissa M. McEwen
Staff Environmental Geologist

Enclosure

c: W.R. Grace PIP Mailing List
W.R. Grace Abutters

G:\10063\078\Notifications\FinalRAMNotice.doc